Nvidia’s top customers are delaying orders of the AI chip leader’s latest ‘Blackwell’ racks due to overheating issues, the Information reported on Monday. The Santa Clara, California-based company’s shares fell more than 4% in early trading.

The U.S. government also said earlier in the day it would further restrict AI chip and technology exports, potentially hurting Nvidia’s sales.

The first shipments of racks with Blackwell chips have been overheating and exhibiting glitches in the way chips connect to one another, the Information reported.

A rack, used in data centers, is a structure that houses chips, cables and other essential equipment.


Major customers Microsoft, Amazon.com’s cloud unit, Alphabet’s Google, and Meta Platforms have cut some orders of Nvidia’s Blackwell GB200 racks, according to the report.

Discover the stories of your interest


Nvidia, Microsoft, Google, Meta and Amazon did not immediately respond to Reuters’ requests for comment. The so-called hyperscalers had each placed Blackwell rack orders worth $10 billion or more, the report said.

Some of the customers are waiting to snag a later version of the racks or plan to purchase the company’s older AI chips, according to the report.

Microsoft was initially planning to install GB200 racks with at least 50,000 Blackwell chips in one of its Phoenix facilities, the report added.

However, key partner OpenAI asked Microsoft to provide it with an older generation of Nvidia’s ‘Hopper’ chips as delays popped up, the report said.

It is unclear how the order cuts would impact Nvidia’s sales as there may be other buyers for the “glitchy” GB200 server racks, the report said.

The company is on track to exceed an earlier target of recording several billion dollars in revenue from Blackwell chips in its fourth fiscal quarter, CEO Jensen Huang said in November.

Huang had also denied earlier media reports of a flagship liquid-cooled server containing 72 of the new chips experiencing overheating issues during initial testing.



Source link

Disclaimer

We strive to uphold the highest ethical standards in all of our reporting and coverage. We StartupNews.fyi want to be transparent with our readers about any potential conflicts of interest that may arise in our work. It’s possible that some of the investors we feature may have connections to other businesses, including competitors or companies we write about. However, we want to assure our readers that this will not have any impact on the integrity or impartiality of our reporting. We are committed to delivering accurate, unbiased news and information to our audience, and we will continue to uphold our ethics and principles in all of our work. Thank you for your trust and support.

admin
admin
Hi! This is Admin.

Popular

More Like this

Nvidia’s biggest customers delaying orders of latest AI racks: report


Nvidia’s top customers are delaying orders of the AI chip leader’s latest ‘Blackwell’ racks due to overheating issues, the Information reported on Monday. The Santa Clara, California-based company’s shares fell more than 4% in early trading.

The U.S. government also said earlier in the day it would further restrict AI chip and technology exports, potentially hurting Nvidia’s sales.

The first shipments of racks with Blackwell chips have been overheating and exhibiting glitches in the way chips connect to one another, the Information reported.

A rack, used in data centers, is a structure that houses chips, cables and other essential equipment.


Major customers Microsoft, Amazon.com’s cloud unit, Alphabet’s Google, and Meta Platforms have cut some orders of Nvidia’s Blackwell GB200 racks, according to the report.

Discover the stories of your interest


Nvidia, Microsoft, Google, Meta and Amazon did not immediately respond to Reuters’ requests for comment. The so-called hyperscalers had each placed Blackwell rack orders worth $10 billion or more, the report said.

Some of the customers are waiting to snag a later version of the racks or plan to purchase the company’s older AI chips, according to the report.

Microsoft was initially planning to install GB200 racks with at least 50,000 Blackwell chips in one of its Phoenix facilities, the report added.

However, key partner OpenAI asked Microsoft to provide it with an older generation of Nvidia’s ‘Hopper’ chips as delays popped up, the report said.

It is unclear how the order cuts would impact Nvidia’s sales as there may be other buyers for the “glitchy” GB200 server racks, the report said.

The company is on track to exceed an earlier target of recording several billion dollars in revenue from Blackwell chips in its fourth fiscal quarter, CEO Jensen Huang said in November.

Huang had also denied earlier media reports of a flagship liquid-cooled server containing 72 of the new chips experiencing overheating issues during initial testing.



Source link

Disclaimer

We strive to uphold the highest ethical standards in all of our reporting and coverage. We StartupNews.fyi want to be transparent with our readers about any potential conflicts of interest that may arise in our work. It’s possible that some of the investors we feature may have connections to other businesses, including competitors or companies we write about. However, we want to assure our readers that this will not have any impact on the integrity or impartiality of our reporting. We are committed to delivering accurate, unbiased news and information to our audience, and we will continue to uphold our ethics and principles in all of our work. Thank you for your trust and support.

Website Upgradation is going on for any glitch kindly connect at office@startupnews.fyi

admin
admin
Hi! This is Admin.

More like this

Sam Altman says ‘no thank you’ to Musk-led group’s...

A group of investors led by Elon Musk...

Steam Deck OLED, ROG Ally and more: all the...

In July 2021, Valve revealed the Steam Deck,...

Popular

Upcoming Events

Startup Information that matters. Get in your inbox Daily!