Micron’s planned $24 billion NAND flash expansion in Singapore will require 400 to 500 power transformers, which is more than double the 100 to 150 units a standard wafer fab typically needs, according to industry sources as reported by DigiTimes. The scale exceeds the annual output capacity of any single Taiwanese transformer manufacturer, turning heavy electrical equipment into a bottleneck for AI-driven semiconductor buildouts.